Skip to content
Free tools

LCOS calculator (levelized cost of storage)

Published LCOS figures disagree mostly because they measure different things. Ember's $65/MWh is the cost of shifting energy; Lazard-style figures add the electricity bought to charge. This calculator gives both from the same inputs, plus the two numbers a project is actually judged against: the capacity payment per kW-month and the price spread it needs.

Project

Equipment, EPC and grid connection per kWh of usable capacity. Ember's October 2025 figure outside China and the US is $125/kWh.

Operation

The share of a full charge used on an average day. Ember assumes 80%.

Used for the cost including charging and the break-even spread. Use your off-peak or solar-hour price.

Levelized cost of storage

Usable capacity
400 MWh
Up-front cost
$50,000,000
Energy delivered in year 1
105,120 MWh
Energy delivered over the project's life
1,747,053 MWh
LCOS, storage only (Ember definition)
$62.7/MWh
LCOS including charging (Lazard definition)
$107.1/MWh
Break-even buy-sell spread
$67.1/MWh
Capacity payment needed
$4.77/kW-month ($4,766/MW-month)
Revenue needed per year, before charging
$5,719,646

Pre-tax, unlevered and in real terms at the discount rate you set. Excludes augmentation, residual value, taxes, land and revenue from ancillary services.

Defaults and sources

Default capex and operating assumptions
$125/kWh all-in project capex (October 2025, outside China and the US: about $75 equipment, $50 EPC and grid connection); 20 years, 90% round-trip efficiency (AC to AC), 80% of one cycle a day, 2% a year degradation, opex 2% of capex a year, 7% discount rate; LCOS $65/MWh excluding chargingEmber, How cheap is battery storage? (December 2025) · checked Nov 10, 2026
Two LCOS definitions
Ember's LCOS is the cost of shifting one MWh and excludes charging electricity; Lazard's is the cost of discharging one MWh and includes itEmber, LCOS calculator methodology · checked Nov 10, 2026

How the calculator works

Each day the battery cycles its usable capacity times the cycle depth and returns that energy times the round-trip efficiency. Capacity falls by the degradation rate every year.

Storage-only LCOS is the present value of capex plus yearly operating cost, divided by the present value of the energy delivered over the project's life. LCOS including charging adds the present value of the electricity bought to charge, which works out to the storage-only figure plus the charging price divided by the round-trip efficiency. That is also the average sale price the project needs.

The break-even spread is that sale price minus the charging price. The capacity payment spreads the present value of capex and operating cost evenly over the project's life at the discount rate, divided by the power rating and by 12 months.

LCOS: common questions

What is the levelized cost of storage (LCOS)?

The lifetime cost of a storage project divided by the energy it delivers, both discounted to today, in $/MWh. Some publishers, such as Ember, leave out the cost of the electricity used to charge it; others, such as Lazard, include it. Check which definition a figure uses before comparing it.

How much does battery storage cost per MWh in 2026?

Ember puts the storage-only LCOS of a utility-scale battery outside China and the US at $65/MWh, based on $125/kWh all-in capex in October 2025. With the same inputs this calculator gives about $63/MWh; Ember does not publish its exact formula. Add the charging cost to compare with a sale price.

Why does LCOS including charging matter?

Because a battery must buy the energy it sells and loses some of it. At 90% round-trip efficiency, charging at $40/MWh adds about $44/MWh to every MWh delivered. That sum is the average price the battery needs to sell at, before any other revenue.

How do I compare LCOS with a capacity tender?

Capacity tenders pay per MW of power per month instead of per MWh. Use the capacity payment figure: it spreads the capex and operating cost evenly over the project's life at your discount rate. A 4-hour battery at the Ember defaults needs about $4.80 per kW-month.

Which inputs move LCOS the most?

Capex, the discount rate and how hard the battery is used. Halving daily use roughly doubles the storage-only LCOS, because the same capital is spread over half the energy. Raising the discount rate from 7% to 10% adds about a fifth.

Related

Newsletter

The weekly brief

Every Tuesday: the 5 stories that matter, India tender awards roundup, one chart we made. Free.

No spam. Unsubscribe in one click.