BESS tariff and LCOS calculator (India)
Indian storage tenders are won and lost on one number: the capacity tariff in rupees per MW per month. This works out the tariff a project needs to recover its capital and running costs, shows what viability gap funding takes off it, and compares it with the tariff in a tender result or your own bid.
Project
Equipment, EPC and grid connection per kWh of usable capacity. Ember's October 2025 figure outside China and the US is $125/kWh.
Operation
The share of a full charge used on an average day. Ember assumes 80%.
Used for the cost including charging and the break-even spread. Use your off-peak or solar-hour price.
Tender
Capital support per MWh of capacity, as stated in the tender. Treated as received up front.
The capacity tariff discovered in an auction or offered in your bid.
Levelized cost of storage
- Usable capacity
- 200 MWh
- Up-front cost
- ₹2,34,00,00,000
- Viability gap funding
- ₹0
- Up-front cost after funding
- ₹2,34,00,00,000
- Energy delivered in year 1
- 52,560 MWh
- Energy delivered over the project's life
- 8,73,526 MWh
- LCOS, storage only (Ember definition)
- ₹5,868.2/MWh
- LCOS including charging (Lazard definition)
- ₹5,868.2/MWh
- Break-even buy-sell spread
- ₹5,868.2/MWh
- Capacity payment needed
- ₹223.07/kW-month (₹2,23,066/MW-month)
- Revenue needed per year, before charging
- ₹26,76,79,446
- Tender tariff
- Enter a tariff to compare
Pre-tax, unlevered and in real terms at the discount rate you set. Excludes augmentation, residual value, taxes, land and revenue from ancillary services.
Defaults and sources
- Default capex and operating assumptions
- Ember's $125/kWh all-in capex for markets outside China and the US, about ₹11,700/kWh at the RBI rate; 90% round-trip efficiency, 80% of one cycle a day, 2% a year degradation, opex 2% of capex a year, 7% discount rate, 20 yearsEmber, How cheap is battery storage? (December 2025) · checked Nov 10, 2026
- Exchange rate for dollar benchmarks
- ₹93.8579 per US dollar (1.00 pm, November 9, 2026)Reserve Bank of India, reference rate (source: FBIL) · checked Nov 10, 2026
- Viability gap funding for grid-scale storage
- ₹14,500 crore for FY 2026-27 to FY 2030-31 to support 92 GWh, including 30 GWh of BESS; capacity allocated by tariff-based competitive bidding; BESS must meet a 40% domestic content requirementUnion Cabinet decision of November 4, 2026 (Prime Minister's Office) · checked Nov 10, 2026
- Two LCOS definitions
- Ember's LCOS is the cost of shifting one MWh and excludes charging electricity; Lazard's is the cost of discharging one MWh and includes itEmber, LCOS calculator methodology · checked Nov 10, 2026
How the calculator works
The capacity payment needed is the present value of capex (less viability gap funding) and yearly operating cost, spread evenly over the contract at your discount rate, then divided by the power rating and by 12 months. That is the tariff in ₹ per MW per month at which the project breaks even before any other revenue.
LCOS divides the same costs by the present value of the energy delivered, with capacity falling by the degradation rate each year. Charging cost is set to zero by default because the buyer supplies the charging energy in many capacity contracts; enter a price if your project buys its own.
BESS tariffs in India: common questions
How is a BESS capacity tariff in ₹/MW/month calculated?
Take the capital cost net of any viability gap funding, add the present value of operating costs, and convert the total into an equal monthly payment over the contract at your cost of capital, per MW of power. At Ember's international capex (about ₹11,700/kWh), a 2-hour battery over 20 years at 7% needs about ₹2.23 lakh per MW per month.
Why does a 4-hour battery need a higher tariff per MW?
Because each MW comes with twice the MWh of batteries. At the same cost per kWh, a 4-hour system needs about twice the monthly payment of a 2-hour one, about ₹4.46 lakh per MW per month at the default inputs, so compare tenders of the same duration.
How much does viability gap funding lower the tariff?
Each ₹1 lakh of VGF per MWh lowers the payment a 2-hour battery needs by about ₹1,570 per MW per month at the default 7% over 20 years. Enter the VGF stated in your tender; it is treated as received up front.
What did the Cabinet approve for energy storage in November 2026?
On November 4, 2026, the Union Cabinet approved a ₹14,500 crore viability gap funding scheme for FY 2026-27 to FY 2030-31 to support 92 GWh of storage: 30 GWh of BESS, 60 GWh of pumped hydro and 2 GWh of other technologies. Capacity is allocated by tariff-based bidding, and BESS projects must meet a 40% domestic content requirement.
Which inputs move the tariff most?
Capex, contract length and the cost of capital. At the defaults, raising the discount rate from 7% to 10% lifts the tariff a 2-hour battery needs from about ₹2.23 lakh to ₹2.68 lakh per MW per month; shortening recovery from 20 to 12 years lifts it to about ₹2.85 lakh.